Historically Sensitive Site: Crown Castle's Communication Antenna Project

Crown Castle was in need of instillation of communication antennas in a historically sensitive site.

AFS 1300

Ballasted System - 90' Tilt-Up Pole
Charlottesville, Virginia
Crown Castle
Completed Installation

The Need

Crown Castle needed to install communication antenna on a 90’ pole in a historically sensitive site. In addition, the site had a small footprint and accessible only over a wooden bridge with a maximum weight of 8 tons. ARE’s foundation and pole system also needed to meet local requirements for aesthetics and paint color.

Overview

Thanks to its Hydraulic System, ARE’s AFS 1300 system can be installed without a crane, in tight spaces, and with limited impact on the environment. Foundation and pole pieces were ferried across the bridge and assembled on site. ARE’s crew installed the system in a 3 days which included OSHA approved railings and ladder, demonstrating ARE’s ability to customize our systems to meet nearly any customer needs.

Project Benchmarks

  • Crew flexibility and equipment availability allowing for installation under time constraints
  • Limited space and access
  • Above ground foundation required no digging on bed of rock

Project Resources

  • 4-person crew
  • 3 days
  • Skid-steer
  • Telehandler
  • Local fill used for ballast

Challenges

  • Limited space and access
  • Quickly deployed in rain and wet conditions
  • Rock base
  • Foundation parts brought across 8T max weight bridge

1 Level Site

Level site for foundation

2 King Post

Set your king-post and attach base trays

3 Truss Arms

Attach truss arms onto base trays

4 Ballast

Attach side walls and add ballast

5 RaisePole

Attach pole sections and raise pole with ARE Hydraulic Ram system